Planning the hiring for a solar farm build
How to map roles to programme milestones, work back from start dates and brief recruitment, with a worked example and a briefing checklist.
Magpie Renewables · Updated 18 November 2026
For project, construction and HR leads
In this guide
06Context
A solar farm is built by a sequence of people, not just a sequence of works. If a site manager arrives after mobilisation, or a commissioning engineer arrives after the commissioning activities they are responsible for have started, the programme absorbs the delay.
This guide shows how to plan hiring against your programme. It includes a worked example you can adapt and a checklist for briefing any recruiter, us included.
1.Start from your programme milestones
List the milestones that change who you need. For a ground-mounted solar farm, these typically include:
- Planning consent
- Grid connection offer and connection date
- Investment decision
- Appointment of the EPC or principal contractor
- Mobilisation to site
- Electrical installation
- Energisation
- Handover to operations
Your programme may name them differently. What matters is knowing which dates are fixed and which can still move. Connection milestones in particular can shift, and hiring for connection-related roles needs to shift with them.
2.Match roles to milestones
For each milestone, ask who must already be in place for it to happen on time.
- Before constructionProject leadership, planning and project controls, commercial and design roles.
- Before mobilisationSite and construction managers, health and safety, supervisors.
- Before electrical works and connectionElectrical and HV engineers.
- Before commissioning activitiesCommissioning and testing roles.
- Before handoverOperations and maintenance staff.
Office roles in finance, HR and project administration often run throughout.
3.Work back from each start date
A role’s lead time is the sum of four parts.
PART 1Search and shortlistingFinding and assessing candidates.
PART 2Interviews and offerYour interview stages, decision and offer.
PART 3Notice periodSet by the candidate’s current contract; often longer for senior roles.
PART 4Pre-start stepsChecks, inductions and any site requirements.
Start the search = date needed − (search + interviews + notice + pre‑start)
4.A worked example
Illustrative only. The project, months and lead times below are invented to show the method. They are not benchmarks. Replace them with your own programme and what you know about each role.
The illustrative project is a ground-mounted solar farm. Mobilisation is planned for Month 6 and energisation for Month 15.
How the months are counted. Month 1 is the first month of the project programme. Month 0 is the month before it, and Month −1 the month before that. So a search that starts in Month −1 begins two months before the programme does.
RoleNeeded byWhy thenIllustrative lead timeStart the search
Project managerMonth 3To lead pre-construction planning4 monthsMonth −1
Planner / project controlsMonth 4To baseline the programme before mobilisation3 monthsMonth 1
Site / construction managerMonth 5To prepare the site a month before mobilisation4 monthsMonth 1
Health and safety managerMonth 5In place for construction-phase planning3 monthsMonth 2
Electrical / HV engineerMonth 9Ahead of electrical installation and connection works4 monthsMonth 5
Commissioning engineerMonth 13Ahead of the commissioning activities they are responsible for3 monthsMonth 10
O&M technicianMonth 14Trained before handover3 monthsMonth 11
How one line is built: the site manager. The illustrative lead time is 17 weeks, about 4 months. To start in Month 5, the search begins in Month 1.
5 wks
3 wks
8 wks
1 wk
- Search and shortlisting: 5 weeks
- Interviews and offer: 3 weeks
- Notice period: 8 weeks
- Checks and inductions: 1 week
What the example shows
- Searches for the first site-based roles begin before most of the site work is visible.
- Several searches overlap, so interview time needs planning too.
- If energisation moves, the commissioning and O&M lines move with it, and the plan should be revisited.
5.Briefing checklist
Use this list before you brief any recruiter.
The project
- Project name, location and stage
- Key milestone dates, and which of them are fixed
- Your organisation’s role: developer, EPC, contractor or operator
The role
- Job title and who it reports to
- What the person must deliver in their first six to twelve months
- Essential experience, and what could come from another industry
- Required qualifications, training courses and site access cards, listed separately
- Working pattern, travel, accommodation and time on site
The offer
- Salary range and benefits
- Vehicle, allowances or other site-related terms
The process
- Required start date, and the latest acceptable date
- Interview stages and who makes the decision
- Interview availability over the next four weeks
- Who approves offers, and how quickly
Constraints
- Right to work, and whether visa sponsorship is available
- Driving licence or other practical requirements
- Any client-specific requirements for the site
6.Context
The government’s UK Solar Roadmap, published in June 2025, sets a 2030 ambition of 45–47GW of solar in Great Britain, ground-mounted and rooftop combined, up from 18GW installed as of the first quarter of 2025. It estimates the solar sector could support up to 35,000 direct and indirect jobs by 2030. More projects means more competition for experienced people, so planning hiring early matters more.
Source: Department for Energy Security and Net Zero, UK Solar Roadmap, June 2025.